Baseline Cost not appearing in EPM schedule

A

Aravind G

Hi,

I use MSP 2007. When I try getting the Baseline Cost from the EPM copy of
the schedule, it is shown as '0' even though the schedule is Baselined and
costs are included.

What could be the issue here? Advance Thanks for anybody who replies.
 
M

Mike Glen

Hi Aravind,

EPM seems to indicate you are using Project Server. If so, try posting on
the microsoft.public.project.server newsgroup (forum). Please see FAQ Item:
24. Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top