Lukey
Hi,
I'm new to MSP (using 2007 standard) so this may seem a stupid questio
but anyhow.....
I have a project set up using resources from a resource pool with cos
rates for each resource. I have set a baseline (and other subsequen
baselines) and the project has progressed (i.e. tasks have been started
money has been spent etc). In the Task Sheet view I can see th
baseline cost for each task. However, in the Resource Sheet view, th
baseline cost for each resource is zero. This results in the whole cos
for each resource showing as variance, which is clearly not the case!
have checked that I am using the correct Cost Rate table for eac
resource and I believe I am.
Can anybody tell me why these baseline values are zero? I am not sur
if this can be corrected or if I have done something wrong earlier
before setting the initial baseline and it is now too late?
By the way, I have added a column for 'baseline 3' in the Resourc
Sheet view and this displays values as expected. I had set up cost
before setting the initial baseline so cannot understand what is goin
on.
Any help will be appreciated
I'm new to MSP (using 2007 standard) so this may seem a stupid questio
but anyhow.....
I have a project set up using resources from a resource pool with cos
rates for each resource. I have set a baseline (and other subsequen
baselines) and the project has progressed (i.e. tasks have been started
money has been spent etc). In the Task Sheet view I can see th
baseline cost for each task. However, in the Resource Sheet view, th
baseline cost for each resource is zero. This results in the whole cos
for each resource showing as variance, which is clearly not the case!
have checked that I am using the correct Cost Rate table for eac
resource and I believe I am.
Can anybody tell me why these baseline values are zero? I am not sur
if this can be corrected or if I have done something wrong earlier
before setting the initial baseline and it is now too late?
By the way, I have added a column for 'baseline 3' in the Resourc
Sheet view and this displays values as expected. I had set up cost
before setting the initial baseline so cannot understand what is goin
on.
Any help will be appreciated