Baseline date headers are not displayed in Project Center Summary View

G

greensp

I changed these Enterprise Global Template date field titles
to appear in the Summary - Project Center view.

Start Current Start
Finish Current Start
Baseline Start 75% Target Start
Baseline Finish 75% Target Finish
Start1 90% Commit Start
Finish1 90% Commit Finish

But in the Project Center view, these header titles are not being displayed,
only the field names.

I read somewhere you can create formulas to equal the value of another date
field.

I see the fields for Start 1 and Finish1 fields under the Import Custom
Field/ Field Type Task
but they do not appear anywhere in the Customize Enterprise Fields Task date
fields.

I have not been able to create a formula to equal the baseline or the
Start1/Finish1
fields. I need to have the titles for the Baseline dates and the Interim
Plan dates appear in the
Project Center views with the headers.

Any suggestions. Need help.

Gwen
 
J

J Baird

Regarding the header title not being displayed...Start1? This looks like a
non-enterprise field. Is "Start1" renamed to "90% Commit Start" in every
schedule that's stored on the Project Server, or just a few of them? If
it's not in every schedule file, how could the Project Server know what
title to display?
 
G

greensp

Yes this is Column is added on our Enterprise Global View
for all projects on the server and we have the column added
in our Project Schedule Template.

The Field Title does not appear in the Project center summary view
 

Ask a Question

Want to reply to this thread or ask your own question?