G
greensp
I changed these Enterprise Global Template date field titles
to appear in the Summary - Project Center view.
Start Current Start
Finish Current Start
Baseline Start 75% Target Start
Baseline Finish 75% Target Finish
Start1 90% Commit Start
Finish1 90% Commit Finish
But in the Project Center view, these header titles are not being displayed,
only the field names.
I read somewhere you can create formulas to equal the value of another date
field.
I see the fields for Start 1 and Finish1 fields under the Import Custom
Field/ Field Type Task
but they do not appear anywhere in the Customize Enterprise Fields Task date
fields.
I have not been able to create a formula to equal the baseline or the
Start1/Finish1
fields. I need to have the titles for the Baseline dates and the Interim
Plan dates appear in the
Project Center views with the headers.
Any suggestions. Need help.
Gwen
to appear in the Summary - Project Center view.
Start Current Start
Finish Current Start
Baseline Start 75% Target Start
Baseline Finish 75% Target Finish
Start1 90% Commit Start
Finish1 90% Commit Finish
But in the Project Center view, these header titles are not being displayed,
only the field names.
I read somewhere you can create formulas to equal the value of another date
field.
I see the fields for Start 1 and Finish1 fields under the Import Custom
Field/ Field Type Task
but they do not appear anywhere in the Customize Enterprise Fields Task date
fields.
I have not been able to create a formula to equal the baseline or the
Start1/Finish1
fields. I need to have the titles for the Baseline dates and the Interim
Plan dates appear in the
Project Center views with the headers.
Any suggestions. Need help.
Gwen