Baseline Date Roll-up Issue in 2007

J

Joe Herlihy

I am evaluating supplier schedules submitted to a prime contractor in a new
technology development project. The suppliers are required to align their
activities with the Prime's activities by placement of Prime activity IDs in
user defined text fields in each supplier's project file.

I am now doing a roll-up of activity status by the Prime's activity ID.

The issue in Project 2007 (12.0.6211.1000) SP MSO (12.0.6425.1000) is that
the summary roll-up picks the LATEST baseline start date - not the earliest.
I have checked this out in a number of different scenarios.

Has anyone else experienced this?
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

Without trying to recreate your scenario, it could be that you are scheduelling from the finish rather than the start. Check in Project/Project Information.../Schedule from:

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



I am evaluating supplier schedules submitted to a prime contractor in a new
technology development project. The suppliers are required to align their
activities with the Prime's activities by placement of Prime activity IDs in
user defined text fields in each supplier's project file.

I am now doing a roll-up of activity status by the Prime's activity ID.

The issue in Project 2007 (12.0.6211.1000) SP MSO (12.0.6425.1000) is that
the summary roll-up picks the LATEST baseline start date - not the earliest.
I have checked this out in a number of different scenarios.

Has anyone else experienced this?
 