Baseline date stamp for reporting - Project Server 2007

G

Georg F

I need to track when baseline cost and finish was changed. This has to be
part of a daily report including a few hundred projects.
Our policies are that in case of a baseline change a copy of the new
baseline will be crated as baseline 1 to 10. Therefore I need to track
whenever a new baseline copy is saved and when.
Is there a field in the project data table that I can use?
Even better, is there a way I can include this information in a particular
project center view?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top