M
Mark Byington
I thought I new how to do this, but am now confused.
PS2003.
I added 'Baseline Start' and 'Baseline Finish' to the TimeSheet view in PWA.
However, I get no values. The fields are blank.
On the global tamplate, I did tools->customize->published Fields. Moved
both from left to right window (column), set as task. pressed default button.
Had PM re-baseline, republish some existing project tasks. Same result.
Fields are blank.
Any and all help, greatly apreciated.
PS2003.
I added 'Baseline Start' and 'Baseline Finish' to the TimeSheet view in PWA.
However, I get no values. The fields are blank.
On the global tamplate, I did tools->customize->published Fields. Moved
both from left to right window (column), set as task. pressed default button.
Had PM re-baseline, republish some existing project tasks. Same result.
Fields are blank.
Any and all help, greatly apreciated.