meg99
using 2003. I have some fixed duration tasks for which the effort is
less than 40 hrs. I have saved a baseline with the baseline start and
finish dates exactly the same as the forecast start and finish dates
(including the time).
I have created a bar to show the baseline. The problem is that the
baseline bar shows longer than the forecast bar.
On some tasks it shows ahead of the bar, on some after the bar.
What gives? Why would the baseline bar show any different than the
forecast bar when the dates and times are exactly the same?
meg99
less than 40 hrs. I have saved a baseline with the baseline start and
finish dates exactly the same as the forecast start and finish dates
(including the time).
I have created a bar to show the baseline. The problem is that the
baseline bar shows longer than the forecast bar.
On some tasks it shows ahead of the bar, on some after the bar.
What gives? Why would the baseline bar show any different than the
forecast bar when the dates and times are exactly the same?
meg99