R
R.Scott Fleming
When in the gantt view and the “baseline†bar is showing(turned on), when I
drag the cursor over the baseline bar, the duration amount/value in the
sub-window is the duration amount of the task not the baseline duration
amount/value.
For example:
A task has a Baseline duration of 4wks
I then adjust the tasks duration to 3wks (example of a tasks duration that
has been improved/reduced...).
When dragging the cursor over the baseline bar, the duration amount in the
sub-window is 3wks (graphically it shows at 4wks and the baseline duration
column amount/value is 4wks).
Curious..
drag the cursor over the baseline bar, the duration amount/value in the
sub-window is the duration amount of the task not the baseline duration
amount/value.
For example:
A task has a Baseline duration of 4wks
I then adjust the tasks duration to 3wks (example of a tasks duration that
has been improved/reduced...).
When dragging the cursor over the baseline bar, the duration amount in the
sub-window is 3wks (graphically it shows at 4wks and the baseline duration
column amount/value is 4wks).
Curious..