I’m having a problem/ question with the baseline rollup option because we
have come across a situation where the Baseline Work on the summary task did
not rollup as expected.
1) How come when we manually enter e.g., Baseline Work (task field), that
the rollup to the summary does sum up when we have the summary task selected
and the option “From subtasks into selected summary task(s)†checked?
2) Is it possible flush out what the baseline value MS Project using on a
task i.e, to restore the original baseline value that was over manually over
written without rebaselining the task (which could be different from the
original baseline)?
3) I was doing some troubleshooting on this issue, and we found that in one
particular instance, MS Project failed to rollup the baseline even though I
did not manually change any of the baseline values. In this case it was the
Baseline Cost field (summary task) that did not sum up. Could be that this
is a bug? We are using MS Pro 2007 SP2.
have come across a situation where the Baseline Work on the summary task did
not rollup as expected.
1) How come when we manually enter e.g., Baseline Work (task field), that
the rollup to the summary does sum up when we have the summary task selected
and the option “From subtasks into selected summary task(s)†checked?
2) Is it possible flush out what the baseline value MS Project using on a
task i.e, to restore the original baseline value that was over manually over
written without rebaselining the task (which could be different from the
original baseline)?
3) I was doing some troubleshooting on this issue, and we found that in one
particular instance, MS Project failed to rollup the baseline even though I
did not manually change any of the baseline values. In this case it was the
Baseline Cost field (summary task) that did not sum up. Could be that this
is a bug? We are using MS Pro 2007 SP2.