Baseline fields not showing in master projects

E

Erkki

Greetings.

I am using a workstation based master project (insert project - read only
mode from 2003 server). My views, tables and filters are working otherwise
properly but on project level the baseline fileds contain zeros or NA:s. Task
level -data is in order. I am strongly suspecting a bug. Answers will be met
with a virtual hug :)

Thank You !

Erkki
 
R

Reid McTaggart

I'm guessing that you have not yet saved a baseline for the project summary.

Select the project summary task.
Tools > Tracking > Save Baseline > Selected Tasks > OK
 
E

Erkki

Thank's a lot Reid !

My original projects were baselined, so I thought it was enough. I baselined
my master project file project by project by selecting the project summary
task. From the second project on, MSP said that I had baselined it already
(baseline fields were empty on project level). So this feature seems to be a
little vague, but no errors...

Erkki
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top