G
George Meriwether
I am trying to get an idea of how much work/revenue has been scheduled
across a large project. When I set my project status date to the end
of the project (no tasks are scheduled past this date) and summarize
the individual tasks using an excel spreadsheet, several individual
tasks are different when comparing BCWS to the Baseline Work. The
figure for the baseline work is the one the project started with and I
believe is correct.
Can anyone provide an expanation?
Thanks in advance.
George M.
across a large project. When I set my project status date to the end
of the project (no tasks are scheduled past this date) and summarize
the individual tasks using an excel spreadsheet, several individual
tasks are different when comparing BCWS to the Baseline Work. The
figure for the baseline work is the one the project started with and I
believe is correct.
Can anyone provide an expanation?
Thanks in advance.
George M.