baseline in tracking gant view

  • Thread starter André Pedro Soares
  • Start date
A

André Pedro Soares

Hi everyone,

I'm working with project 2002 that permits to save a set of baselines, How
do I select in tracking Gantt view to switch the baseline that appears in
gray bars.

Regards
 
J

John Beamish

Format | Bar Styles
In the Name column, locate "Baseline"
In the From column, change "Baseline Start" to "Baseline1 Start" (or
whatever baseline is appropriate)
In the To column ... well, it's obvious what to do here.

JLB, PMP
 