TroyS,
If you are looking for the baseline assignment information on a daily basis,
you can not accurately get this information. This is because when you
create a baseline, it only saves the following fields for an assignment:
start, finish, work, cost, & cost per use. It does not split the task due
to either resource availability or the calendar. On the other hand, the
msp_web_work table does split the task.
So if a resource is scheduled to work 4 hours on Thursday, 4 hours on
Friday, and 5 hours on Monday, the msp_assignments table will have one entry
for the assignment and the assignment's baseline information. The
msp_web_work table will have two entries, one for Thursday and Friday
totaling 8 hours and one for 5 hours on Monday, but no baseline information.
This is why we use the msp_web_work table to get our timephased information.
The best we can do with the baseline information in the msp_assignments
table and assume that the assignment's baseline work is equal every day
(which may not be accurate), after we take into account the proper
calendars.
I believe that Microsoft left out the ability to timephase the baseline
because I think this information is of little value. Very few tasks start
on the original baseline date, sometime the start early, and sometimes they
start late. If a task starts one day early, a resource will show actual
work on a day that they were baselined as having none. On a report, this
looks bad, but in reality, it is very good!
If you or your management insist on having this report, the best way is to
have a complete copy of the plan saved when you want to create the baseline.
The easiest way to do this using Project Server is to create a new archive
version. (In PWA, Admin - Manage enterprise features - Versions.) You can
call this new version .Baseline. This new "project plan" is loaded into the
OLAP cube, so it is available for the Portfolio Analyzer views. No OLAP
extension necessary! If you don't want these .Baseline plans to appear in
Project Center views, you can filter them out.
I hope this helps.
--
Ed Morrison
msProjectExperts
"We wrote the books on Project Server"
http://www.msprojectexperts.com
FAQ -
http://www.projectserverexperts.com