Baseline info not appearing in Timesheet View

M

M Colodzin

I added the Baseline Start and Baseline Finish dates to the Timesheet View.
Both Columns appear in the timesheets, but neither contain any data (they're
all blank.) I've baselined my plan and confirmed that the baseline
information is present and correct in the Project Center - Task Tracking View.

Anyone experienced this and know how to make that data appear in the
timesheet view?
 