R
R Wood
I was wondering why my exported timephased data always showed
baselined values (work, BCWP) as zero. Back tracking, I noticed that
my Project Stats showed NA or 0 for baseline values (start, finish,
duration, etc.). And yet I had baseline values (work, duration,
start, finish, cost) for all tasks.
I made a copy of my schedule and started to play around with the
data. I deleted all the baseline values then took another baseline
(Tools/Tracking/Save Baseline/Entire Project). I noticed that the
baseline values of some of my tasks weren't getting updated. I can
delete the baseline values and repeat this over and over again.
Always the same tasks are missed (the first 37 of my schedule).
However, if I select these tasks then take another baseline
(Tools/Tracking/Save Baseline/Selected Tasks), then the baseline
values are updated for these tasks. And yet, my Project Stats still
show NA or 0 for the project's baseline values.
Anyone know what's wrong?
Rob Wood
baselined values (work, BCWP) as zero. Back tracking, I noticed that
my Project Stats showed NA or 0 for baseline values (start, finish,
duration, etc.). And yet I had baseline values (work, duration,
start, finish, cost) for all tasks.
I made a copy of my schedule and started to play around with the
data. I deleted all the baseline values then took another baseline
(Tools/Tracking/Save Baseline/Entire Project). I noticed that the
baseline values of some of my tasks weren't getting updated. I can
delete the baseline values and repeat this over and over again.
Always the same tasks are missed (the first 37 of my schedule).
However, if I select these tasks then take another baseline
(Tools/Tracking/Save Baseline/Selected Tasks), then the baseline
values are updated for these tasks. And yet, my Project Stats still
show NA or 0 for the project's baseline values.
Anyone know what's wrong?
Rob Wood