Baseline Reference Points

S

Scheduler5

There are 20 reference points that get saved when setting the baseline.
Apparently dependencies are not one of them. Does anyone know what the 20
primary reference points are? I don't want the categories, I want the actual
reference points.
 
A

Andrew Lavinsky

Just insert a field in the table of any view and review what comes up in the
pick list under "Baseline." Do so in a Task and Resource view to get the
complete list.

But no, dependencies are not kept as part of the baseline. For that level
of detail, you may opt to save a copy of your file, then use the Compare
Project Versions utility to capture any deltas.
 
R

Rod Gill

If you need to copy dependencies, copy the predecessors field to Text1 or
any of the other 29 text fields.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Andrew Lavinsky said:
Just insert a field in the table of any view and review what comes up in
the
pick list under "Baseline." Do so in a Task and Resource view to get the
complete list.

But no, dependencies are not kept as part of the baseline. For that level
of detail, you may opt to save a copy of your file, then use the Compare
Project Versions utility to capture any deltas.



__________ Information from ESET Smart Security, version of virus
signature database 5024 (20100413) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5024 (20100413) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top