J
Jim Aksel
I have a task with one resource assigned. When I baseline this task (it is
0% complete), I see a baseline cost of $28000 in the Gantt view. I switch to
task usage view and insert the Baseline Cost column I can now see each
resource assigned to a task. My one resource assigned to this one task is
showing $32600 while the line immediately above it (the task name) continues
to show $28000.
I manually verified that $32600 is correct and that MSP is correctly
weighting each baseline hour against the $/hr over the time phase. The rate
increases....
If I look at the $28000 and divide it by the task hours, the resulting
hourly wage is less than the smallest value I've entered into the Cost Rate
Table A. I have verified I am making calculations against the single saved
baseline, EV method is %Complete against the same baseline.
Can anyone explain why the sum total of all resources applied to one task
would not sum up correctly to a total task cost? When I baselined, I
verified the roll-up boxes were selected.
0% complete), I see a baseline cost of $28000 in the Gantt view. I switch to
task usage view and insert the Baseline Cost column I can now see each
resource assigned to a task. My one resource assigned to this one task is
showing $32600 while the line immediately above it (the task name) continues
to show $28000.
I manually verified that $32600 is correct and that MSP is correctly
weighting each baseline hour against the $/hr over the time phase. The rate
increases....
If I look at the $28000 and divide it by the task hours, the resulting
hourly wage is less than the smallest value I've entered into the Cost Rate
Table A. I have verified I am making calculations against the single saved
baseline, EV method is %Complete against the same baseline.
Can anyone explain why the sum total of all resources applied to one task
would not sum up correctly to a total task cost? When I baselined, I
verified the roll-up boxes were selected.