M
Michael
Hi All,
I'm trying to track contract hours, actual hours worked, and the difference
in 3 different columns on the task sheet view. I have the following columns
in my task view: Work (which I use for entering in contracted hours),
Baseline Work (where I enter the actual hours), and Work Variance (which
shows the difference of Work - Baseline Work). The columns for Work and Work
Variance are rolling up all of the hours entered by line item and that is
what I want. But the hours entered in Baseline Work are not rolling up to the
parent task with a total. Should I be using other fields to do this? Like I
said, I just need a column to enter in hours, a column to enter in actual
hours, and a third that shows the difference. And I need all of the columns
to show a roll up of hours.
Thanks for the advice!
Michael
I'm trying to track contract hours, actual hours worked, and the difference
in 3 different columns on the task sheet view. I have the following columns
in my task view: Work (which I use for entering in contracted hours),
Baseline Work (where I enter the actual hours), and Work Variance (which
shows the difference of Work - Baseline Work). The columns for Work and Work
Variance are rolling up all of the hours entered by line item and that is
what I want. But the hours entered in Baseline Work are not rolling up to the
parent task with a total. Should I be using other fields to do this? Like I
said, I just need a column to enter in hours, a column to enter in actual
hours, and a third that shows the difference. And I need all of the columns
to show a roll up of hours.
Thanks for the advice!
Michael