I had the same problem with Project 2007 and Project Server 2007 and found a solution that had nothing to do with the baseline.
In the group permissions in Project Server, make sure that the "My Projects" category for the "Project Managers" group has all the "Resource" permissions enabled:
1. Edit timesheet
2. Approve timesheet
3. Assign resource
3. Create supplementary timesheet
4. Modify enterprise business resource
It's possible that not all of these permissions are needed but it worked for me.
Cheers.
chicagohunte wrote:
Baseline Save Error
10-Dec-08
A user is getting "Cannot Clear or Save Baseline. You do not have the
adequate permission to clear or save baselines to baselines 0-5". Baseline
can be saved by someone with elevated permissions but this user has the
permission to save a protected baseline. Thoughts?
Previous Posts In This Thread:
Baseline Save Error
A user is getting "Cannot Clear or Save Baseline. You do not have the
adequate permission to clear or save baselines to baselines 0-5". Baseline
can be saved by someone with elevated permissions but this user has the
permission to save a protected baseline. Thoughts?
Sounds like they may not have all the permissions you think they have.
Sounds like they may not have all the permissions you think they have
Do they belong to a group or have category set which denies saving a
baseline
If so, remove them from that group. For example if they belong to admin and
team member and the team member is explictly denied that ability then even
though they are an admin they won't be able to do what an admin is typically
able to do
-Jack Dahlgre
???
I'm have the same issue. PMs are receiving the warning:
Cannot Clear or Save Baseline.
You do not have the adequate permission to clear or save baselines to baselines
0-5.
They are a part the Project Manager group. I set permission for this group using the Project Manager Template. From other posts I have read, the permission required is under Global Permissions -> Projects -> Save Unprotected Baseline. The PM template defaults this as allowed, but my PMs are still seeing the warning.
Any help would be great!
ps - Project Server 2007; XP; Window SharePoint; PWA
Submitted via EggHeadCafe - Software Developer Portal of Choice
Six Free Visual Studio 2010 MSDN Memberships Giveaway
http://www.eggheadcafe.com/tutorial...al-studio-2010-msdn-memberships-giveaway.aspx