Baseline SavedDate

Y

Yashr

Hello-

I am trying to see where in SQL server the date when all our baselines were
saved is stored. We have MS Project 2003. I see I can use
Application.ActiveProject.BaselineSavedDate(i) thru VBA. But, we need this
date in sqlserver for some other custom work we are doing.

Thanks.
 
E

Ed Morrison

Unfortunately, I believe this field is stored in the binary in
msp_projects.reserved_binary_data.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top