I am using MS Project 2007 enterprise edition. For the purpose of reports, I
included particular category projects in a master project. When I add
additional columns ( say for instance baseline start or start variance), the
value shows NA even though the sub-project has baselines and variances. I
even tried unchecking the Option in Calculations - Inserted Projects are
calculated like summary tasks.
Do I need to make any other changes to show those dates/information while
they are in the master project?