Baseline Start & Finish dates in Resource Time Sheet

N

Nitesh Mathur

Hi All

I'm using EPMS 2003 and facing one problem:
I want to display baseline start & baseline finish dates in resource
timesheet (In Project Web Access 2003), for this I have added both the fileds
from Admin --> manage views and both the fileds are now display in resource
time sheet but there contents still blank. As entire project plan is
baselined and published.
When I open project plan baseline dates (baseline Start & Finish) are
display but not display in resource time sheet.

Please help.
 
J

Jonathan Sofer

Try adding those fields to the published fields list under
Tools>Customize>Published Fields
 
N

Nitesh Mathur

Thanx Jonathan for Immediate response

It's working and display dates on task level but its not display dates on
summary level / sub task. Can u please help me again.
 
J

Jonathan Sofer

What options did you choose when you set the published field? Task or
Assignment?
 
J

Jonathan Sofer

Try changing the option to publish "Assignment" level, this will at least
show you the lowest level baseline dates which are at the assignment level
(i.e. Resource/Task relationship)

This might show the task level as well. Not sure why you aren't seeing the
summary information data.

See if changing the option to "Assignment" level does the trick.
 