N
Nitesh Mathur
Hi All
I'm using EPMS 2003 and facing one problem:
I want to display baseline start & baseline finish dates in resource
timesheet (In Project Web Access 2003), for this I have added both the fileds
from Admin --> manage views and both the fileds are now display in resource
time sheet but there contents still blank. As entire project plan is
baselined and published.
When I open project plan baseline dates (baseline Start & Finish) are
display but not display in resource time sheet.
Please help.
I'm using EPMS 2003 and facing one problem:
I want to display baseline start & baseline finish dates in resource
timesheet (In Project Web Access 2003), for this I have added both the fileds
from Admin --> manage views and both the fileds are now display in resource
time sheet but there contents still blank. As entire project plan is
baselined and published.
When I open project plan baseline dates (baseline Start & Finish) are
display but not display in resource time sheet.
Please help.