Hi,
I am facing a very strange problem within a custom "task usage" view that I'
ve created. In the right pane I have three timephased fields (work, baseline
work and actual work). When I first add resources to tasks and save baseline
everything works great and the baseline work data are distributed normally in
the respective line next to the resource name and also in the summary tasks
lines. A few days after saving and publishing the project to the Project
Server 2007, I opened the project from the PrjProfessional and the timephased
baseline data had disappeared. However, the total values of baseline work
(shown in the respective column at the left pane) were all still there. In
other words, I cannot see the distribution of baseline work into time
schedule.
Do you have any idea what might causing this misfunctionality??
I forgot to say that I have also a similar problem in a task usage view that
shows timephased cost data. In this case I can see the timephased baseline
cost data next to the resource, but they don't roll up to the tasks, summary
tasks and project summary task.
Any help would be great!
I am facing a very strange problem within a custom "task usage" view that I'
ve created. In the right pane I have three timephased fields (work, baseline
work and actual work). When I first add resources to tasks and save baseline
everything works great and the baseline work data are distributed normally in
the respective line next to the resource name and also in the summary tasks
lines. A few days after saving and publishing the project to the Project
Server 2007, I opened the project from the PrjProfessional and the timephased
baseline data had disappeared. However, the total values of baseline work
(shown in the respective column at the left pane) were all still there. In
other words, I cannot see the distribution of baseline work into time
schedule.
Do you have any idea what might causing this misfunctionality??
I forgot to say that I have also a similar problem in a task usage view that
shows timephased cost data. In this case I can see the timephased baseline
cost data next to the resource, but they don't roll up to the tasks, summary
tasks and project summary task.
Any help would be great!