F
Frederic
Hi All,
I wish to update the baseline work for a project without doing a "save
baseline" because it will delete some manually entered baselines at a task
level. Is there a way to manually update this information at the project
level: in PWA, in the project server view, all my baselines are set to 0
because - i guess - no "save baseline" has been done by the PMs.
Cheers,
Fred
I wish to update the baseline work for a project without doing a "save
baseline" because it will delete some manually entered baselines at a task
level. Is there a way to manually update this information at the project
level: in PWA, in the project server view, all my baselines are set to 0
because - i guess - no "save baseline" has been done by the PMs.
Cheers,
Fred