Baseline Work in Project Server DB

J

JMB

Thanks to the project server documentation
(PJSVRDB.HTM#findTimephasedProject) I can extract from the database the
actual, scheduled, and overtime hours spent by task, resource, project
and day. The problem is that I need the baseline work by task,
resource, project and day. Where can I find this information? Can I
find this info. What is baseline work, how can I calculate it manually
if I have the scheduled and actual hours? I appreciate any replies.
 
R

Rod Gill

You can't calculate baseline hours. Baseline hours are stored only after you
select Tools, Tracking, Save Baseline. The baseline saves a snapshot of your
schedule at specific times such as after the schedule is approved. Note that
there are 11 baselines you can save to.

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 
M

Mike Glen

Hi JMB,

Next time, try posting on the server newsgroup as this one is closing down.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top