Darrell
All,
I have found a situation where the Baseline Work for some schedules does not
appear in the Data Analysis views even though it is viewable both in Project
Pro and in the PWA Project Center. And, I have schedules where the Baseline
Work appears in Project Pro, PWA Project Center and the Data Analysis views.
The only difference that I think exists between these schedules is when the
baseline was applied. I know that the schedules that DO show baseline work in
the data analysis views had a baseline set prior to the schedules being
published to the server. And, I believe the schedules that are NOT showing
baseline work data had the baseline information applied after they already
existed on the server.
I know this because there was no baseline data appearing in the Project
Center views for some projects so I requested the PMs be sure they were
“rolling up baseline data to all summary tasks†when adding tasks to their
schedules. Now these schedules show baseline data in the Project Center views
but still do not show data in the Data Analysis views.
Any idea what may be wrong or how to correct this?
Darrell
I have found a situation where the Baseline Work for some schedules does not
appear in the Data Analysis views even though it is viewable both in Project
Pro and in the PWA Project Center. And, I have schedules where the Baseline
Work appears in Project Pro, PWA Project Center and the Data Analysis views.
The only difference that I think exists between these schedules is when the
baseline was applied. I know that the schedules that DO show baseline work in
the data analysis views had a baseline set prior to the schedules being
published to the server. And, I believe the schedules that are NOT showing
baseline work data had the baseline information applied after they already
existed on the server.
I know this because there was no baseline data appearing in the Project
Center views for some projects so I requested the PMs be sure they were
“rolling up baseline data to all summary tasks†when adding tasks to their
schedules. Now these schedules show baseline data in the Project Center views
but still do not show data in the Data Analysis views.
Any idea what may be wrong or how to correct this?
Darrell