Hiii
I'm using Project Server 2003 , presently I'm facing a problem which is very
critical to me.
In many project plan Baseline Work(in Hrs) shows different in Portfolio
Analyzer , Project Central and Project Professional 2003.
Like if we r talking about project plan A , when I open this plan in Project
Pro 2003 its baseline work is 2021 hrs or when I see this plan in portfolio
analyzer its shows 1773hrs and when I see this plan in Project Central its
shows 1326hrs.
I'm confuse where I did mistake as entire project plan was baselined.
Kindly provide the solution,so that baseline work will be display same in
any view either its Portfolio analyzer / Project Central or Project Prof 2003
..
I'm using Project Server 2003 , presently I'm facing a problem which is very
critical to me.
In many project plan Baseline Work(in Hrs) shows different in Portfolio
Analyzer , Project Central and Project Professional 2003.
Like if we r talking about project plan A , when I open this plan in Project
Pro 2003 its baseline work is 2021 hrs or when I see this plan in portfolio
analyzer its shows 1773hrs and when I see this plan in Project Central its
shows 1326hrs.
I'm confuse where I did mistake as entire project plan was baselined.
Kindly provide the solution,so that baseline work will be display same in
any view either its Portfolio analyzer / Project Central or Project Prof 2003
..