Baseline Work Mismatch in PWA & Project Prof 2003

N

Nitesh Mathur

Hiii

I'm using Project Server 2003 , presently I'm facing a problem which is very
critical to me.

In many project plan Baseline Work(in Hrs) shows different in Portfolio
Analyzer , Project Central and Project Professional 2003.
Like if we r talking about project plan A , when I open this plan in Project
Pro 2003 its baseline work is 2021 hrs or when I see this plan in portfolio
analyzer its shows 1773hrs and when I see this plan in Project Central its
shows 1326hrs.
I'm confuse where I did mistake as entire project plan was baselined.

Kindly provide the solution,so that baseline work will be display same in
any view either its Portfolio analyzer / Project Central or Project Prof 2003
..
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top