Baseline Work not display in resource sheet

N

Nitesh Mathur

Hi,

I'm using Project Professional 2003 and suffering with a problem that when I
want to see Baseline work resource wise in Project Prof 2003 (Resource Sheet)
, I'm unbale to see baseline work in resource sheet .
As I already baseline the entire schedule and in Gant chart view Baseline
work shows task wise but not as resource wise in resource sheet.
Same thing happen in Project Web Access 2003 (Project Central --> Rescource
wise baseline work view)
And this is happen with 2-3 project plans only not all projects.

Please help me.
 
N

Nitesh Mathur

Dear Gary

Thanks for reply, but my problem is still presist -- I have added baseline
work in Resource usage sheet but its shows only assignment level if we
collapse the resource assignments then Baseline Work not shows (as total) in
front of resource name.

Please help again.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top