Baseline Work Recalculates

J

john

Hell Fellow Project Users,

I have noticed in one of my projects that the Baseline Work recalculates
after I accept and approve updates from my resources. The Work and Actual
Work is good.

Any Ideas?

Also, this symptom is hapeening to another user but the actual work is not
matching their resources tasksheet, it seems to be spreading the hours. I
know he was having a decimal issue, but we fixed it by manually going in.

Any ideas on this one too?

Thanks
John
 
B

Ben Howard

Hi John,

This is weird. Do you have any formulas or VBA on the project that is
causing the baseline to be calculated?
 
J

john

Hi Ben,

No special VBA code. I have a few indicator formulas calculating on the
baselinework field. However, when I look at old projects everything was
good, but the symptom seems to be happening after I installed the
infrastructure update. Our Project Server 2007 environment sits on top of
MOSS with WFE, APP and DB servers.

Any other suggestions,
Thanks
John
 