Baseline Work values inconsistent

N

nick_cam

Hi,

I'm doing some reporting which includes the Baseline work field.

The problem I have is that in some project plans the Total baseline
work (according to the Gantt View) does not equal the sum of all the
resources baseline work (according to the Resource Usage view). I'm
under the impression that each resource's baseline work added together
on a project should equal the total baseline.

Another problem is that The total baseline in the Project plan for some
plans is completely different to what is displayed in PWA (Projects
tab, status reporting view), is there any way to fix this link as they
should be displaying the same values???

Thanks in advance,
Nick
 
N

nick_cam

Just got PWA to mtach up to the plans, so don't need help with that.
Still need to find out why the resource's baseline work is not adding
up to the overall plan's though.

Thanks,
Nick
 