Ritesh
Hi,
I am just curious to know how does Microsoft Project treat multiple
baselines. Say I saved first baseline in June, second in July and third
in August. In the EV reports will it take the data from the latest
baseline? Also how do I ensure that I am working on latest baseline.
The project Statistics tab shows only the original baselined dates and
not the latest one
Any help is appreciated.