S
Sam
I need to ask about baselines whether in project professional 2003 or project
professional 2007.
just suppose i have a one project in which i saved three baselines of
different dates.
1st jan, 2nd jan , 3rd jan
but after few days i want to open view--->table --> variance .
in this view from which date of baseline show values . and how i can select
different baselines to see in variance view.
may be i want to see a variance view with 2 jan . and may be a 3rd jan .
pls reply me soon.
professional 2007.
just suppose i have a one project in which i saved three baselines of
different dates.
1st jan, 2nd jan , 3rd jan
but after few days i want to open view--->table --> variance .
in this view from which date of baseline show values . and how i can select
different baselines to see in variance view.
may be i want to see a variance view with 2 jan . and may be a 3rd jan .
pls reply me soon.