B
Basem
I'm a Project 2002 user, I did a plan for this year,
when I add the actual work hours on the Task Usage View, I
have a problem of changing finish date field for the same
row. Is there any setting there to stop this changing and
can I copy the baseline finish date column to finish date
column.
Regards,,,
when I add the actual work hours on the Task Usage View, I
have a problem of changing finish date field for the same
row. Is there any setting there to stop this changing and
can I copy the baseline finish date column to finish date
column.
Regards,,,