Baseline

B

Basem

I'm a Project 2002 user, I did a plan for this year,
when I add the actual work hours on the Task Usage View, I
have a problem of changing finish date field for the same
row. Is there any setting there to stop this changing and
can I copy the baseline finish date column to finish date
column.

Regards,,,
 
G

Gérard Ducouret

Hello Basem,

Don't try to copy the baseline finish date column to finish date column.
That's not he way MS Project works.
If you want that the task keeps its Duration while you enter Actual Work,
you can set its Task Type parameter to Fixed Duration in the Task
Information dialog box, Advanced tab. (Double Click on the task row)

Gérard Ducouret
 