Baselined plan - remaining work

D

Dasani

Once you baseline a plan you are able to track variances. Is there a
way to baseline Remaining Work (Expected time to compl) as I only see
Baseline Work. I need to baseline the remaining work column so we can
track variances

Thanks
 
R

Rod Gill

Hi,

That doesn't make sense. What variance are you trying to measure? If its the
change week by week, save the value in one of the custom Numbern fields.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top