D
Dasani
Once you baseline a plan you are able to track variances. Is there a
way to baseline Remaining Work (Expected time to compl) as I only see
Baseline Work. I need to baseline the remaining work column so we can
track variances
Thanks
way to baseline Remaining Work (Expected time to compl) as I only see
Baseline Work. I need to baseline the remaining work column so we can
track variances
Thanks