R
Renee H
We are using PS2007 SP1 and recently noticed an issue. We have a project
that uses a calendar that has Thanksgiving and the day after Thanksgiving as
nonworking days. When we saved this file to the server, we saw no change to
the baselined information upon opening from the server. We then repointed
the external predeccessors to projects on the server and saved and still saw
no change. But when we reopened the project, the baseline work was changed
to include the day after Thanksgiving. The scheduled work still showed no
hours (not even zero) for the 2 nonworking days. So we tried to rebaseline.
The baseline hours for the day after Thanksgiving then showed zero (not blank
as expected). Any ideas?
that uses a calendar that has Thanksgiving and the day after Thanksgiving as
nonworking days. When we saved this file to the server, we saw no change to
the baselined information upon opening from the server. We then repointed
the external predeccessors to projects on the server and saved and still saw
no change. But when we reopened the project, the baseline work was changed
to include the day after Thanksgiving. The scheduled work still showed no
hours (not even zero) for the 2 nonworking days. So we tried to rebaseline.
The baseline hours for the day after Thanksgiving then showed zero (not blank
as expected). Any ideas?