Baselines????

S

Sameer

Altough i have denied saving baselines on the global permissions for Project
managers, they can still save the baselines.

Does any one know what i am doing wrong here?

Regards
 
R

Ray McCoppin

If the project doesn't have a baseline they will still be able to save the
baseline the first time. After that they will not be allowed to rebaseline
the project.

The security item should be name re-baseline project.

Hope this helps
 
R

Ray McCoppin

If the project doesn't have a baseline the will still be able to save a
baseline the first time. After that they will not be able to re-baseline the
project.

Hope this helps.
 