Baselines

V

Verossa

Hell

I have the following scenario

(1) Project plan complete and baseline
(2) Project tasks have changed and baseline start/finish saved into interim plan start1/finish

Question: How do I re-establish the baseline start/finish? Actually, if I had a number of interim plans on a project how do I switch from one to the other

Thanks in advance to all who respond
Vers
 
S

Sean

Verossa:

Project stores information from baselines and interim
plans for comparison purposes only. You can't revert to
a plan at Point X based on baselines or interim plans
you've saved. Though, you can insert fields that relate
to those baselines/interim plans.

If you're using Project locally, try saving as a new
project each time you save a baseline or interim plan.
This way you'll be able to "revert" to your Project at a
given point in time.

If you're using a newer version of Project on an
enterprise platform, you can save the file as a different
version. Talk to your server admin about this.

Hope this helps!

----------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com
-----Original Message-----
Hello

I have the following scenario:

(1) Project plan complete and baselined
(2) Project tasks have changed and baseline start/finish
saved into interim plan start1/finish1
Question: How do I re-establish the baseline
start/finish? Actually, if I had a number of interim
plans on a project how do I switch from one to the other?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top