Baselining specific tasks DECREASES overall summary costs

R

Roland

I am baselining a specific task which should increase the baseline cost of
the project. When I baseline the task, Project is decreasing the overall
cost by a considerable amount (more than I'm adding).

I am using the "Selected Tasks" -> "To all summary tasks" option.

Not sure what is going on. I'm working in 2003 project server environment.

Any suggestions as to what is going on?
 
M

Mike Glen

Hi Roland,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
R

Roland

Hi Mike,

Thanks for replying. I checked out the newsgroup and discovered that it is
the same one we are in! I went there and using the links made a big loop
right back into this discussion group.

So, is there anybody out there that has a suggestion on what is causing this
problem in Project?
 
M

Mike Glen

Not true, Roland, you still need the microsoft.public.project.server
newsgroup which is where the server gurus hang out!

Mike Glen
Project MVP
 
R

Roland

OK. So you're saying its a server issue rather than a project issue?
Posted same question in the server group as well.

RC
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top