I am baselining a specific task which should increase the baseline cost of
the project. When I baseline the task, Project is decreasing the overall
cost by a considerable amount (more than I'm adding).
I am using the "Selected Tasks" -> "To all summary tasks" option.
Not sure what is going on. I'm working in 2003 project server environment.
Any suggestions as to what is going on?