J
Joseph Peter
Hi All,
I am Joseph Peter. One of the issues I ran into is related to the Baselining
of a current project. Few uncertanities regarding the Cost & Schedule
prevented me from Baselining the project at the begining. Now the project is
over 3 months. How can Cost and effort changes have undergone 2 revisions in
2 mpp files. How can I compare the current mpp with those in the previous
ones? I experimented with baseline.
I did one experiment by taking the mpp file offline.
I saved a local copy of the mpp file, deleted all the tasks, copied the
tasks from revision 1 mpp, saved the baseline. I repeated the same for
revision 2. Then I copied back the current tasks with actuals and saved the
baseline.
It didn't help me.
Let me know your thoughts.
Thanks in advance,
Joseph Peter
I am Joseph Peter. One of the issues I ran into is related to the Baselining
of a current project. Few uncertanities regarding the Cost & Schedule
prevented me from Baselining the project at the begining. Now the project is
over 3 months. How can Cost and effort changes have undergone 2 revisions in
2 mpp files. How can I compare the current mpp with those in the previous
ones? I experimented with baseline.
I did one experiment by taking the mpp file offline.
I saved a local copy of the mpp file, deleted all the tasks, copied the
tasks from revision 1 mpp, saved the baseline. I repeated the same for
revision 2. Then I copied back the current tasks with actuals and saved the
baseline.
It didn't help me.
Let me know your thoughts.
Thanks in advance,
Joseph Peter