R
robert
Im new to project and im not to hot with project management
terminology so forgive me.
I have a task that will last 2 days. I know that this task will occur
between two dates and the duration between those dates is 10 days.
How can i show on my Project that the task in only 2 days but will
occur in this 10 day period.
Thanks in advance.
Robert, Inverness.
terminology so forgive me.
I have a task that will last 2 days. I know that this task will occur
between two dates and the duration between those dates is 10 days.
How can i show on my Project that the task in only 2 days but will
occur in this 10 day period.
Thanks in advance.
Robert, Inverness.