S
sChapman
I have started using Project since last week only. I have a project
plan, but a resource has requested a days holiday. This is in the
middle of a task. How can I account for this in the plan please?
Ideally I want to avoid increasing the duration of the task but some
how account for the fact that the resource didn't work on it for a
day.
Thanks
plan, but a resource has requested a days holiday. This is in the
middle of a task. How can I account for this in the plan please?
Ideally I want to avoid increasing the duration of the task but some
how account for the fact that the resource didn't work on it for a
day.
Thanks