S
storm
Hi chaps
I'm having a bit of a blonde moment here!
I'm about to start planning this fiscal year's work programme and I'm
struggling with it.
I'll start with an example
Project A has 10 tasks. The dev manager reckons it will take 166 days
to complete the work. I.E. if we started it today it would be all done
in 166 days time. But the dev boys wouldn't be working on it 100% of
their time, they will be working on other projects at the same time.
So, the 166 days should be written into which column on my plan? I
thought it should go into Duration. And the actual time to do the
work? The dev manager tells me "this chunk of work will take 5 weeks,
and this one will take 2 weeks" Where do I put that?! I created a
column called "Work" but entering values into that alters the Duration,
and I don't want that.
Many thanks for your suggestions and advice!
lynne
I'm having a bit of a blonde moment here!
I'm about to start planning this fiscal year's work programme and I'm
struggling with it.
I'll start with an example
Project A has 10 tasks. The dev manager reckons it will take 166 days
to complete the work. I.E. if we started it today it would be all done
in 166 days time. But the dev boys wouldn't be working on it 100% of
their time, they will be working on other projects at the same time.
So, the 166 days should be written into which column on my plan? I
thought it should go into Duration. And the actual time to do the
work? The dev manager tells me "this chunk of work will take 5 weeks,
and this one will take 2 weeks" Where do I put that?! I created a
column called "Work" but entering values into that alters the Duration,
and I don't want that.
Many thanks for your suggestions and advice!
lynne