S
saws
I have two resources in one of my tasks in the schedule : X and Y.
X has baseline work against his name as per the schedule while Y has actual
work - which means X was scheduled to be working but Y is working instead.
Now I want to delete resource X from the schedule since he is not working. I
tried lots of things (like changing the allocation, changing the baseline
work assignment etc) but I cannot figure out a way to do this without
affecting either the % complete or the duration of the schedule.
Logically there should not be any change to the schedule because everything
else is the same.
Any ideas on how to achieve this?
Thanks!
X has baseline work against his name as per the schedule while Y has actual
work - which means X was scheduled to be working but Y is working instead.
Now I want to delete resource X from the schedule since he is not working. I
tried lots of things (like changing the allocation, changing the baseline
work assignment etc) but I cannot figure out a way to do this without
affecting either the % complete or the duration of the schedule.
Logically there should not be any change to the schedule because everything
else is the same.
Any ideas on how to achieve this?
Thanks!