P
Peter M.
Hello there.
What is in your opinion the best way to handle basic work load of resources
in project server? First, we set up a project with all resource names as
tasks, all assigned 10% of work to sort of simulate their estimated basic
work load of 10%.
But a problem came up with that solution. When a resource is on holiday, it
will - logically - always be overallocated and be displayed red in every
view, which harms clarity.
Now we think about setting max. units to only 90%. Is that meant to be the
best solution?
What suggestions do you have?
Thanks for your help,
Peter.
What is in your opinion the best way to handle basic work load of resources
in project server? First, we set up a project with all resource names as
tasks, all assigned 10% of work to sort of simulate their estimated basic
work load of 10%.
But a problem came up with that solution. When a resource is on holiday, it
will - logically - always be overallocated and be displayed red in every
view, which harms clarity.
Now we think about setting max. units to only 90%. Is that meant to be the
best solution?
What suggestions do you have?
Thanks for your help,
Peter.