J
John Noel
Hi All,
This is a question sent to me by one of our PMs. I am just
a techy trying to help our PMs anyway I can and so I am
looking for any help you can offer
Question
In a project plan a second baseline was created. Now the
following Cost related columns show zeroes; BCWP, ACWP,
SPI, CPI and EV. There is however data in these columns;
Projected costs, Cost Variance, Estimate at Completion and
Variance at Completion. Note the Estimate at Completion
and Variance at Completion are the same figure.
Are the missing columns running on a template based on
the "Baseline" Column while the project is now baselined
on "Baseline2"?
How can I get the BCWP, ACWP, SPI, CPI and EV colums to
show calculated values and not zeros?
Thanks,
John
This is a question sent to me by one of our PMs. I am just
a techy trying to help our PMs anyway I can and so I am
looking for any help you can offer
Question
In a project plan a second baseline was created. Now the
following Cost related columns show zeroes; BCWP, ACWP,
SPI, CPI and EV. There is however data in these columns;
Projected costs, Cost Variance, Estimate at Completion and
Variance at Completion. Note the Estimate at Completion
and Variance at Completion are the same figure.
Are the missing columns running on a template based on
the "Baseline" Column while the project is now baselined
on "Baseline2"?
How can I get the BCWP, ACWP, SPI, CPI and EV colums to
show calculated values and not zeros?
Thanks,
John