I think of it this way. BCWS is your bid to do the work. BCWP is the value
of what you accomplished.
Example: I bid to paint a fence at $25/hr and I believe I can paint
10ft/hr. Since there is 100 Feet of fence my bid is: $25/hr x 1hr/10ft x
100 feet = $250. That is I estimate that I can paint the fence in 10 hours.
My bid is $2.50/foot =$250. Let's assume I do the work myself (I'd
actually pay the painter $15/hr but that will make it too complicated).
So, I work 4 hours and actually paint 60 Feet of fence.
BCWS = 4hr x 10ft/hr x $2.50/foot = $100 the value of my scheduled work.
BCWP is the value of what I performed (using the same rules as BCWS).
BCWP= 60 ft x $2.50/ft = $150. I would expect to be paid this much, it is
the value of what I performed.
Actual Cost of Work Performed (ACWP) = $25/hr x 4 hours = $100 (I did the
work)
Other trivia:
Cost Performance Index (CPI)=BCWP/ ACWP = 150/100 = 1.50 (>1 is good, I am
under running)
Schedule Performance Index BCWP/BCWS = 150/100 = 1.50 (I am 50% ahead of
schedule, greater than 1 is good).
If I paid the painter to do it, ACWP=4x15=$60 and CPI=150/60=2.5 while SPI
stays the same.
At this rate, I will expect to finish early and with a total cost of less
than my bid. So I will make more money than I planned.
I always ask myself the question: "If I had to bid what I just
accomplished, what would have I bid using my original rules?" That is the
value of BCWP.
You can learn a lot more about this by using the search term "Earned Value
Management" in the Project Help files or on the search engine of your choice.
There is a good book on the market called "Earned Value Project Management"
by Quentin Flemming. It is available at amazon or at
www.pmi.org (go to
their bookstore).
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project