No offense intended but you are using BWCP in a very strange way it
appears, at least as far aas I can tell. Budgeted Cost of Work
Performed is fundamentally the cost of the work involved in doing the
task - it is actually a measurement of schedule performance with the
work done by the resource, expressed in terms of the dollars you've paid
to do it, plus materials consumed. That is why you cannot ignore the
time phasing of the task - BWCP is fundamentally time phased data and
without the time information it is essentially meaningless. This is
the opposite of what you say you're doing when you say the work is
overhead and not part of the task. The cost of the task is in fact the
cost necessary to accomplish the work of getting the parts, NOT the cost
of the parts being ordered. The parts cost is figured into the cost of
the task later on that actually consumes them, not the task that
acquires them.
Where did the figure $18,000 for Monday come from anyway? You said
three days for $30 in parts. Disregarding that this is the wrong place
in the budget (IMHO) to reflect that cost anyway, $18k after day 1
doesn't jive with anything - the part was $20k, so that says Mon should
get $20k, the total was $30k, prorating gives $10k for Mon. The other
options are to accrue the total cost at either the start or end of the
task - that says either Mon gets the whole $30k or Wed (day 3) gets the
whole amount. But no schedule I can see comes up with $18k for Mon.
I'm building a brick walkway. I earn $10/hour. It takes me a day to
locate and order the special bricks we want, including a $25 in phone
calls to track down the only dealer in North America that carries this
special brick. I order $5000 worth. My bricklayer gets $25 / per hour
and after the bricks arrive it takes him 3 days to lay all the bricks.
My project has two tasks...
1. Order 500 bricks @ $10 per brick - duration 1 day - cost $105, $80
labour plus $25 phone, prorated
2. Lay bricks - duration 3 days - cost $5600, $600 labour plus $5000 br
icks, prorated
1 day into the bricklaying task, assuming everything on schedule, BWCP
will be $80 + $200 + $25 + $5000/3 or about $1972.
or, my original bricklayer has gotten sick and I had to substitute one
who gets $30 per hour. At the end of Day 1 of bricklaying the BCWP is
still $1972 but the ACWP is now $2012. We're on schedule but over
budget.
Hope this helps
--
Steve House
MS Project MVP
Visit
http://www.mvps.org/project/faqs.htm for the FAQs