R
Rickey Dharna
I have been using MS Project/Project Server for several years and I never ran
into this problem before. Essentially, I created a project plan, added
resources with cost, and baselined it. Now I am halfway through the project
with several tasks completed. For some of the completed tasks, EV is
calculated correctly. However, for some other completed tasks, it shows the
BCWP as 0 which is not corrent because the task was worked on and completed.
They were also baselined. Does anyone know why BCWP would be zero
considering other tasks are being calculated correctly?
into this problem before. Essentially, I created a project plan, added
resources with cost, and baselined it. Now I am halfway through the project
with several tasks completed. For some of the completed tasks, EV is
calculated correctly. However, for some other completed tasks, it shows the
BCWP as 0 which is not corrent because the task was worked on and completed.
They were also baselined. Does anyone know why BCWP would be zero
considering other tasks are being calculated correctly?