D
DJ Huff
I cannot figure out how BCWP is calculated. I have a consistent set up with
% Complete as the EV method. Is % Complete the Actual Duration / Duration?
I have one task where the BCWS seems to use % Work Complete rather than %
Complete while others use a % I cannot find nor figure out. MS Project Help
does not give enough information to allow me to consistently calculate BCWP.
I have some errors after baselining and I need to find how the core elements
are truly calculated so I can tell what I have to do to get the indexes
correct (SPI, CPI). I know how those are calculated, but don't know what to
adjust to get the indexes back in line.
Your advice is appreciated.
% Complete as the EV method. Is % Complete the Actual Duration / Duration?
I have one task where the BCWS seems to use % Work Complete rather than %
Complete while others use a % I cannot find nor figure out. MS Project Help
does not give enough information to allow me to consistently calculate BCWP.
I have some errors after baselining and I need to find how the core elements
are truly calculated so I can tell what I have to do to get the indexes
correct (SPI, CPI). I know how those are calculated, but don't know what to
adjust to get the indexes back in line.
Your advice is appreciated.