D
Doctor Lard
Hi folks,
I've seen similar posts to this in the past and the problem has always been
down to lack of a baseline, wrong status date, that kind of thing.
Well I'm relatively earned value savvy and and believe I have done all the
right things but I'm still getting zero BCWP when I use Physical % Complete
rather than % Complete as the basis for my EV calculations.
If I swap a task back to use % Complete then BCWP is fine.
Swap it back to use Physical % Complete and it zeroes again.
I've checked and re-checked the data but really have run out of ideas.
So; any help would be appreciated.
Thanks in advance.
Doc.
I've seen similar posts to this in the past and the problem has always been
down to lack of a baseline, wrong status date, that kind of thing.
Well I'm relatively earned value savvy and and believe I have done all the
right things but I'm still getting zero BCWP when I use Physical % Complete
rather than % Complete as the basis for my EV calculations.
If I swap a task back to use % Complete then BCWP is fine.
Swap it back to use Physical % Complete and it zeroes again.
I've checked and re-checked the data but really have run out of ideas.
So; any help would be appreciated.
Thanks in advance.
Doc.